| Client | Object | Fuel | Capacity of boilers | Project term |
| JSC "GECO Kaunas" | Installation of a new boiler-house with flue gas condenser (Kaunas) | Wood chips | 2x8 MW | Executing |
| State Enterprise "Visagino energija" | Installation of a boiler-house with flue gas condenser (Visaginas) | Wood chips | 8 MW | Executing |
| Public Enterprise "Rokiskio psichiatrijos ligonine" |
Modernization of the boiler house, work project and reconstruction works (Rokiskis) | Wood chips | 900 kW | Executing |
| JSC "Utenos silumos tinklai" | Reconstruction of the boiler-house by installing a hot-water boiler (Utena) | Wood chips | 8 MW | 2012 |
| JSC “Taurages silumos tinklai” | Reconstruction of the boiler-house by installing a hot-water boiler (Taurage) | Wood chips | 2 MW | 2012 |
| JSC “Grigiskes” | Boiler plant modernization by installing a steam boiler (Grigiskes) photo » | Wood chips | 26 t/h, 25 bar, 250 °C |
2010 |
| JSC “Radviliskio siluma” | Installation of hot-water boilers with flue gas condenser and CHP unit (Radviliskis) photo » | Wood chips, peat and crushed straw |
2x5 MW | 2009 |
| JSC “Sakiu silumos tinklai” | Installation of hot-water boiler in Gelgaudiskis (Sakiai) photo » | Straw | 4x470 kW | 2007 |